RM3.6 Million Road Upgrading Project For Three Villages In Tarat
TARAT: The RM3.6 million road upgrading project linking Kampung Tarat Sibala, Kampung Tarat Melawi, and Kampung Tarat Mawang is set to improve connectivity facilities and comfort for residents in the area.
The project, under the Greater Kuching Coordinated Development Agency (GKCDA), involves upgrading and resurfacing a 3.2 km stretch of existing road, alongside the construction of drainage systems and culverts.
Minister for Education, Innovation and Talent Development, who is also GKCDA Chairman, Dato Sri Roland Sagah Wee Inn said implementing the project is among ongoing efforts to improve infrastructure facilities in the Tarat constituency.
He said this when speaking at the GKCDA Project Site Handover Ceremony at Kampung Tarat Sibala Hall on Friday.
According to him, claims that development is not being carried out in the Tarat area are baseless, as various infrastructure upgrading efforts have been implemented to improve residents' facilities.
He said road conditions in the area have changed significantly compared to the past, with most previously gravelled roads now upgraded and paved.
He noted that infrastructure development efforts also involve other areas, including the Plaman Nyabet/Sira/Krian route to Tiang Bukap, which subsequently connects to the Puncak Borneo area.
The ceremony also witnessed the handover of the Letter of Acceptance from Serian District Council to the contractor appointed to execute the project.
The project has a 12-month implementation period running from 20 November, 2026, to November 2027.
Its implementation is expected to benefit residents of all three villages, particularly in terms of road safety, smoother daily movement, and access facilities between village areas.
For the record, a total of 19 development projects worth RM180.9 million in total have been identified under GKCDA for the Tarat constituency.
Of that total, two projects worth RM2.8 million have been completed, while nine projects worth RM137.8 million are being implemented on schedule and seven projects worth RM24.25 million are still in the planning stage.
The implementation of these projects involves cooperation among several implementing agencies, including the Public Works Department, Rural Water Supply Department, Serian District Council, Department of Agriculture, Department of Irrigation and Drainage, and the Land Custody and Development Authority (LCDA). — UKASnews