New SMK Bukit Goram To Accommodate 1,115 Students, Ease Overcrowding
KAPIT: The new construction of Sekolah Menengah Kebangsaan (SMK) Bukit Goram worth RM96.79 million will provide capacity for 1,115 students to ease student enrolment pressure at existing secondary schools in Kapit Division.
Works Minister Dato Sri Alexander Nanta Linggi said the new school is much needed as existing secondary school capacity is increasingly unable to cope with student enrolment demand.
According to him, the school is designed to accommodate 1,080 mainstream students and 35 special education needs pupils (MBPK).
He said this when speaking at the Letter of Acceptance handover and groundbreaking ceremony for the project at Kampung Kemarau on Friday.
In a related development, he disclosed that savings of about RM40 million from the project allocation compared to the tendered price could potentially be used to build teachers' quarters and a student hostel, subject to approval from the relevant ministries.
He also expressed hope that the contractor can complete the project six months ahead of the stipulated schedule based on its track record in executing past projects.
The project will have a 182-week construction period and is scheduled for completion on May 16, 2030.
The development on the 7.19-hectare site comprises an administration block, an academic block with 36 classrooms, a Secondary Integrated Special Education Programme (PPKI) block with five classrooms, a canteen, a school hall, toilets, and other supporting facilities.
Meanwhile, Malaysian Public Works Director-General Dato Ir Ibrahim Esa stressed that all parties involved must ensure the project is executed according to schedule, specifications, and stipulated quality standards.
He also reminded the contractor and the Project Director to carry out their responsibilities professionally and with integrity, as well as to monitor work progress and identify site issues early to avoid delays.
The project's implementation also emphasises the target of zero sick projects and early completion through cooperation between the Ministry of Education (MOE), the Ministry of Works (MOW), the Public Works Department (JKR), and the contractor.
Also present were Deputy Minister in the Sarawak Premier’s Department (Law and Native Customs) Datuk Jefferson Jamit Unyat, and Malaysian JKR Education Works Branch Director Dato Ir Ahmad Nadzri Abdul Majid. — UKASnews